Drax £20bn AI Data Centre Info

Drax’s £20 Billion AI Data Centre: What Is Being Built in Yorkshire?

A power station near Selby could host one of Britain’s largest AI computing campuses. Here’s what the investment would pay for, how much power the project aims to use and what still needs approval.

The announcement

A new AI campus beside a working power station

Drax, Brookfield and Radiant have agreed to pursue a large data centre development on the Drax Power Station estate near Selby. The £20 billion figure describes what the full buildout could attract, not a completed investment.

Potential full investment>£20bn

Brookfield estimate, including computer chips

Initial compute capacity100MW

Targeted first phase

Target openingQ1 2028

Dependent on approvals and customer commitments

The development timetable, as proposed on 3 November 2026How the proposed campus could develop100 MW500 MW>1 GWUp to, first phaseFurther capacity aimLong-term total ambitionFrom Q1 20282028 to 2031After 2031Milestones are targets, not completed construction or confirmed installed capacity100 MWFirst phaseTarget opening Q1 2028Subject to approvals and tenant500 MWFurther capacity ambition2028 to 2031>1 GWEventual total ambitionPotential expansion after 2031Targets, not built capacity
Drax RNS uses an initial 100MW target, a later 500MW capacity ambition and a possible total above 1GW after 2031. All stages remain conditional.
Not approved or operational yet. Drax says planning, regulatory clearance, network approval, a suitable tenant and each partner’s final investment decision are required. Its regulatory announcement sets out those conditions.
Money and ownership

Who is backing the £20bn project?

The agreement separates the roles of the energy company, infrastructure investors and data centre developer.

Land and powerDrax

Site, grid connection, planning and power integration

CapitalBrookfield + Qai

Joint venture expected to back development

AI infrastructureRadiant

Design, operations and search for customers

What the headline investment figure actually meansA potential investment programme, not a £20bn chequeEarly phaseEntire project£2.5bn initial potentialMore than £20bn projected in fullFull programme includes computing chips, buildings and infrastructure.Every stage needs commercial and regulatory sign-off.Potential investment£2.5bnInitial phase estimateSubject to conditions>£20bnPossible full programmeIncludes computing chipsA forecast, not an expenditure totalor unconditional funding commitment
Illustrative comparison of the scale of possible investment. Brookfield’s full-project estimate includes semiconductor chips; it is not a sum already invested.

Brookfield puts possible investment for the first stage at £2.5 billion. The much larger overall figure includes the semiconductor chips required to operate AI systems, so it should not be read as a £20 billion construction contract or as funding already spent.

The attraction is not simply another building. AI training and cloud services need powerful computers connected by high-capacity fibre. Our guides on why so many data centres are being built and the fibre networks needed for AI centres explain the wider demand.

Electricity and connectivity

Why build it at Drax Power Station?

The North Yorkshire site already has land, major electrical infrastructure and access to the national fibre network. Those things can take years to secure at a new location.

Why the power station site matters4 GW2.6 GW100 MWExisting grid accessActive generationProposed Phase 1Connection capability atthe power stationCurrent power stationgenerating capacityTarget compute capacityto be supplied by gridThree numbers that mean different things4 GW is not the data centre’s planned power consumption4 GW2.6 GW100 MWGrid connectionActive power generationPhase 1 compute targetNot reserved solely for computingat the future data centreExisting power station capacity,not a new data centreTo use grid power at first,subject to approvals
Grid access and existing generation are site infrastructure figures, not statements of the data centre’s electricity use. Phase 1 is expected to import power from the grid.

Existing site

1,000+ acres

Drax’s industrial estate has substantial land and cooling infrastructure.

Electricity

First phase: grid

The first phase would draw power from the grid. Later phases could use on-site generation directly if approved.

Network links

Fibre nearby

Large AI facilities need rapid, reliable links to other data centres and internet networks.

Later phases could use a behind-the-meter power arrangement, but Drax says this would require additional consents. The site’s 4GW grid connection is not a forecast of electricity consumption. Related coverage explains why power connections matter to UK data centre projects.

Benefits and questions

What could it mean for Yorkshire?

Drax says the project could secure the future of the power station site and protect hundreds of jobs. The plans also raise practical questions about power, noise, water and the surrounding environment.

Issue
What is proposed
What remains uncertain
Jobs
Protect existing roles and support new work
No final permanent job total published
Electricity
Import from grid first; possible direct generation later
Actual yearly demand and later approvals
Community
Consultation and voluntary benefits fund
Fund details and full local impacts still to be decided
Environment
Assess flood risk, noise, wildlife and visual effects
Detailed assessment will accompany planning

Why this matters: The first phase is proposed on an existing industrial site, but that does not remove the need for scrutiny. Drax’s public consultation page invites questions on local impacts, including environmental assessments.

Status on 4 November 2026

What has to happen before construction?

  1. 01
    Local consultation

    Drax’s project page lists drop-in sessions at Drax Village Hall on 19 and 20 November, with consultation closing 3 December 2026.

  2. 02
    Planning and network approvals

    A Phase 1 planning application is being prepared. Regulatory and network permissions are also required.

  3. 03
    Customers, contracts and final approval to invest

    The partners need an acceptable tenant and commercial agreements before committing to the first construction phase.

Early 2028 is therefore the intended opening date, not a promise. The development might eventually exceed 1GW, but its later phases depend on separate decisions. For broader context, read about faster UK approvals for major data centres and the rise of AI traffic on the internet.

Ties the meerkat, Find Cheap Broadband mascot
Ties’ take · Bottom line

A big ambition, with important steps still ahead

What Drax already has is a large power-connected site and investors willing to explore its potential. What it does not yet have is a fully approved £20bn data centre. The first 100MW phase is the immediate test: permission, a customer and a final investment decision must come before the computers arrive.

Common questions

Drax data centre FAQs

Is Drax building a £20 billion data centre in Yorkshire?

Drax, Brookfield and Radiant announced a partnership on 3 November 2026. Investment across the full potential project could exceed £20 billion, but construction, approvals, tenants and final funding decisions are not yet secured.

Where will the Drax AI data centre be built?

The proposed first phase is within the existing Drax Power Station estate near Selby in North Yorkshire.

When will the Drax data centre open?

The partners are targeting commercial operations for the first 100MW phase in the first quarter of 2028, subject to planning, regulatory and network approvals, a tenant and final investment decisions.

How much electricity will the Drax data centre use?

No verified annual electricity consumption figure has been published for the completed development. The 100MW first-phase compute target, the station’s 4GW grid connection and its 2.6GW generating capacity are different measures.

Who will pay for the Drax AI data centre?

Brookfield and Qatar-based Qai are expected to provide capital through their AI infrastructure joint venture. Drax contributes land and energy infrastructure, while Brookfield-backed Radiant leads AI data centre design and customer engagement.

Will the Drax project create jobs?

The partners say the proposal could protect hundreds of existing jobs and create further work in the area. An exact confirmed number of new permanent jobs has not been published.

Can residents comment on the Drax data centre plans?

Yes. Drax’s project website lists consultation events on 19 and 20 November 2026 and a consultation deadline of 3 December 2026, ahead of a planning application.