How Much Electricity Do Data Centres Use?

How Much Electricity Do Data Centres Use? UK, US and Global Figures

Data centres are consuming more electricity as cloud services and AI expand. The latest national and worldwide studies show how much they use, where the demand is concentrated and what might happen by 2030.

The latest figures

How much electricity do data centres use each year?

The latest published estimates put annual data centre electricity consumption at 4.46 terawatt-hours in Great Britain, 192 TWh in the United States and 485 TWh worldwide. The first two figures describe 2024. The global estimate covers 2025, which is the more recent worldwide benchmark published by the International Energy Agency (IEA).

A terawatt-hour (TWh) is one billion kilowatt-hours (kWh). These figures measure electricity used over an entire year, not the amount of power a data centre draws at one moment.

GREAT BRITAIN · 20244.46 TWhDESNZ meter-based estimate of grid electricity for certain commercial data centres
UNITED STATES · 2024192 TWhBerkeley Lab national model, approximately 4.7% of US electricity use
WORLDWIDE · 2025485 TWhIEA global estimate, up 17% from its 2024 figure
These are not identical measurements. The British estimate excludes Northern Ireland, enterprise data centres and electricity not taken from the grid. The US total is a model covering a broader range of data centres, while the IEA constructs a global estimate. Do not add the regional totals together or compare them as though their coverage were identical.

For a same-year global reference, the IEA estimated 415 TWh in 2024. The different reporting years and definitions matter more than an extra decimal place.

Great Britain

UK data centre electricity use has risen 41% since 2020.

Britain’s first detailed national meter-based series shows electricity consumption rising by 41% from 2020 to 2024, with an unusually heavy concentration around London and Slough.

How the Great Britain total changed from 2020 to 202402.55.03.1620203.4020213.7820224.0620234.462024TWh per year20203.1620213.4020223.7820234.0620244.46TWh per year
DESNZ estimates of electricity taken from the public grid, TWh per year. Values for 2020 to 2023 are rounded from the official series. The 2024 figure is 4.46 TWh, commonly rounded to 4.5 TWh.

The Department for Energy Security and Net Zero (DESNZ) estimated that data centres in Great Britain used 4.46 TWh from the public electricity grid in 2024. That was approximately 1.8% of the 249.2 TWh recorded in its grid-consumption dataset, rounded to 2% in the government’s summary. It was 41% higher than in 2020.

Geography explains much of the local impact. Facilities in the South East consumed roughly 1.8 TWh, while London accounted for about 1.7 TWh. Together, they made up 77% of the identified data centre electricity use. Slough alone accounted for around 1.3 TWh, or 29% of the Great Britain total.

Where Great Britain’s data centre electricity was used in 2024
South East
1.8 TWh
London
1.7 TWh
Elsewhere in GB
1.0 TWh

Rounded DESNZ regional figures. These shares represent data centre demand captured by the study, not the whole electricity market.

There is a scope limitation behind the headline. DESNZ only counted identified facilities providing services to external customers, including colocation, managed hosting and large cloud data centres. In-house enterprise sites were outside the study, as were unmatched facilities and electricity generated on site. It is a lower-bound style estimate for the defined population, not a complete meter reading for every data centre in the UK.

That distinction explains why some earlier industry forecasts quoted larger numbers. For example, National Energy System Operator modelling used data centre capacity and assumed utilisation to produce an estimated 7.6 TWh for 2023, whereas the DESNZ meter-based figure for 2023 was 4.1 TWh. Different methods, not proof that either number describes the same facilities.

The clustering is relevant to ongoing plans for faster approval of major UK data centres and National Grid connections for new facilities. National electricity shares can look small even when the pressure on a few local substations is substantial.

United States

US data centres used 192 TWh in 2024, with much more growth projected.

America’s 2026 federal research update points to significantly faster growth, while warning that the next few years depend on server shipments, cooling systems and how quickly new sites actually open.

US data centre electricity use: now and in 20302024 estimated2030 reference case192 TWh649 TWh2030 modelled range521843 TWh2024 estimated192 TWh2030 reference case649 TWh2030 plausible range521843Based on 2026 Berkeley Lab models
The 2024 estimate is retrospective. The 2030 reference case and scenario range are forecasts from the Lawrence Berkeley National Laboratory report published in June 2026. Bar widths share the same 843 TWh scale.

Lawrence Berkeley National Laboratory’s June 2026 report revised its estimate of US data centre electricity consumption in 2024 to 192 TWh, equivalent to about 4.7% of national electricity use. The updated study excludes cryptocurrency mining.

Its central model suggests consumption could reach 649 TWh by 2030, equal to 11.8% of projected US electricity use. Other scenarios range from 521 to 843 TWh, or approximately 9.5% to 15.3%. Those are forecasts, not guaranteed construction plans or a reading from the electricity grid.

The June 2026 update also revised some earlier estimates following changes to GPU shipment data and assumptions about AI inference servers. That is why older headlines quoting 183 TWh for US data centres in 2024 do not necessarily match the newer federal modelling.

Rising demand is particularly difficult where data centres cluster. High-demand facilities may need additional transformers, transmission infrastructure and local power supply. Developers are increasingly under scrutiny too, as illustrated by New York proposals to pause new AI data centres and the Palm Beach County data centre moratorium debate.

Worldwide

Global data centre electricity use reached 485 TWh in 2025.

The IEA says global demand rose sharply in 2025. Its 2030 baseline is about twice today’s level, although the precise outcome remains uncertain.

The global outlook, measured in terawatt-hours each year05001,000415485950202420252030 forecast2024 estimated2025 estimated2030 projected415 TWh485 TWh950 TWhIEA forecast, not observed use
The 2024 and 2025 values are IEA estimates. The 2030 value is the IEA 2026 base-case projection, not a measurement or a guaranteed outcome. Solid marks are estimates; the dashed line indicates the forecast.

In its 2026 Key Questions on Energy and AI analysis, the IEA estimated that the world’s data centres consumed 485 TWh in 2025. That is 17% above its 415 TWh estimate for 2024. Electricity used by AI-focused data centres grew faster, increasing by around 50% over the same year.

The agency’s central projection is 950 TWh by 2030, about 3% of forecast worldwide electricity consumption. That projection is close to the IEA’s earlier estimate of 945 TWh, but incorporates more recent information about investment, chip supply and constraints on bringing new electrical infrastructure online.

Data centres already host much more than AI: cloud storage, business software, streaming systems, financial services and web platforms all rely on them. For a closer look at changing workloads, see what AI traffic means for the internet, how inference traffic works and how much bandwidth AI uses.

A country’s share of global demand also varies by the study used. The IEA previously estimated that the United States accounted for about 45% of global data centre electricity use in 2024, based on its own international model. That percentage should not be recalculated by directly dividing Berkeley Lab’s differently modelled US figure by the IEA world total.

Inside the data centre

Why do data centres need so much electricity?

Electricity demand rises for two reasons: the computers are doing more work, and the buildings must keep that equipment operating reliably.

Computing and storage

Processors, memory, storage drives and networking equipment run digital services around the clock.

Cooling and airflow

Heat from dense server racks has to be removed. Cooling demand varies with equipment and climate.

Power delivery

Backup systems, electrical conversion, lighting and other site equipment also draw electricity.

The servers are usually the largest direct load. Electricity also runs storage, network equipment and the cooling needed to remove heat. A useful efficiency measure is power usage effectiveness (PUE), which compares a whole facility’s energy use with the energy supplied to its IT equipment. A lower PUE generally indicates less energy spent on overheads, but it does not tell you how efficiently the computing work is being done.

AI training and inference can require dense arrays of accelerators, but a data centre is not automatically an AI facility. Better-performing hardware can reduce the energy required for a task while total electricity demand still rises if the number and complexity of tasks increase.

Whether the expansion raises electricity bills is a separate question. It depends on how grids charge for new connections, where generation is built, investment in local networks and whether data centres pay the full costs associated with their load. A countrywide 2% share does not tell you what happens in a particular town.

Electricity is only one environmental consideration. Water consumption depends on the cooling system, local weather and where the electricity comes from. We have a separate guide to whether ChatGPT uses a lot of water. Physical networks matter too, including why AI data centres need additional fibre-optic links.

  1. 01
    Check the reporting year.

    A figure published in 2026 may describe electricity consumed in 2024 or 2025. It is not a real-time 2026 total.

  2. 02
    Check which buildings count.

    Great Britain’s metered commercial-site series is narrower than US and global energy models. Scope determines what the number can support.

  3. 03
    Keep forecasts separate.

    The 2030 numbers depend on demand, technology, grid capacity and future construction. They should never be presented as electricity already consumed.

Ties the meerkat, Find Cheap Broadband mascot
Ties’ take · Bottom line

The numbers are growing. The measurement methods matter.

In the latest published research, data centres used 4.46 TWh in Great Britain in 2024, 192 TWh in the United States in 2024 and an estimated 485 TWh worldwide in 2025. Each figure covers a defined market, year and methodology. The next question is not simply how much electricity facilities use, but whether power networks can support their concentration and growth.

Common questions

Data centre electricity FAQs

How much electricity do data centres use in the UK?

DESNZ estimates 4.46 TWh of electricity taken from the grid by identified commercial data centres in Great Britain in 2024. It excludes Northern Ireland, in-house enterprise data centres and certain unmatched or self-supplied sites.

What percentage of UK electricity is used by data centres?

The DESNZ figure is approximately 1.8% of 249.2 TWh of Great Britain grid electricity in 2024, commonly rounded to 2%. The study is narrower than a full UK-wide accounting of every data centre.

How much electricity do data centres use in the US?

Lawrence Berkeley National Laboratory estimated 192 TWh in 2024, approximately 4.7% of US electricity use. Its June 2026 report projects a central 2030 total of 649 TWh, with a wide scenario range.

How much electricity do all data centres worldwide use?

The International Energy Agency estimated 485 TWh in 2025, up from 415 TWh in 2024. Its updated 2030 central projection is around 950 TWh.

How much of data centre electricity is used by AI?

There is no single reliable worldwide percentage for all AI tasks. Data centres also run cloud storage, streaming, websites and other services. The IEA reports that electricity demand from AI-focused centres grew about 50% during 2025.

Why do different reports give different UK data centre figures?

Studies count different facilities and use different approaches. DESNZ matches commercial data centre addresses with actual grid meters, while some other estimates model installed power capacity and assumed utilisation. They are not interchangeable.

Will data centres use twice as much electricity by 2030?

The IEA forecasts roughly 950 TWh of global use in 2030 versus 485 TWh in 2025, which is close to a doubling. That is a central projection, not a confirmed future result.

Does a 1 GW data centre use 1 TWh a year?

Not necessarily. A continuous 1 GW load for 8,760 hours would use 8.76 TWh in a standard year, but actual energy consumption depends on average load and utilisation. GW measures power; TWh measures electricity used over time.