National Grid Signs Deal for Giant UK Data Centre Project

National Grid Signs Deal for Giant UK Data Centre Project

National Grid has agreed to buy land at Teesworks for a huge electricity substation linked to a proposed AI data-centre development. The land deal is real. The data-centre operator, final power demand and opening date are not yet confirmed.

Land agreement

What exactly has National Grid signed?

On 1 November 2026, Sky News reported that National Grid Electricity Transmission had agreed to purchase more than 70 acres at Dorman Point from the Teesworks site partnership. The land is intended for a substantial new electricity substation, not for National Grid to operate an AI data centre.

National Grid’s head of lands, Matt Pearce, confirmed that securing the land agreement was a step towards the substation. Teesworks said remediation and site preparation would be needed before handover.

One agreement, two very different projects
Reported land agreement · Teesworks70+acres at Dorman Point

For the planned National Grid substation. This is not the whole Teesworks estate or a measured data-centre footprint.

AgreedLand purchase

National Grid and Teesworks, reported 1 Nov 2026.

Not announcedData-centre buyer or operator

No named hyperscaler, confirmed final investment or operational date.

Source: Sky News, 1 Nov 2026, citing National Grid and Teesworks statements. Land acquisition, planning approval and a commissioned data centre are separate milestones.
Separate data-centre applicationReserved matters approved

Teesworks received council approval on 1 August 2025 for a data-centre campus under application R/2025/0382/ESM.

National Grid substation applicationStill under consideration

The 400kV substation outline application, R/2026/0711/OOM, has no recorded decision as of 1 November 2026.

The difference matters. An approved data-centre layout does not grant consent for National Grid’s separate electricity project, and neither record proves that an AI tenant has committed to the site.

Electricity infrastructure

How would the giant substation support a data centre?

Large AI clusters need reliable, high-capacity electricity. National Grid proposes a 400kV transmission substation at Dorman Point. Its public project list calls it the Tees Dock substation. Steel River Power already operates a private electricity network across the wider Teesworks estate.

An illustrative electricity path
National Grid transmission

High-voltage electricity brought into the wider area.

Proposed Tees Dock substation

Planned 400kV grid connection and transformation infrastructure.

Potential AI campus

Further distribution, buildings and tenant arrangements would still be required.

Separate data path

Servers would also need resilient high-capacity fibre routes to other networks. Electricity and internet connectivity solve different problems.

Conceptual power route only, not a verified engineering drawing. Specific connection design, timing and final tenant remain to be confirmed.
400 kVVoltage specified in the application

A design voltage. It does not state how many megawatts a future data centre will draw.

Up to 3.2 GWPotential site capacity quoted by the mayor

Ben Houchen gave this figure to Sky News. It is not a measured load or a guarantee of delivered data-centre capacity.

Why does land for a substation matter so much?

A suitable power connection can take years to develop. A project needs land, planning consent, specialised equipment and a feasible grid connection long before servers can be switched on. The electricity constraint is separate from the bandwidth used by AI services or the traffic generated when a model answers questions.

Why the national grid queue is in focus
125 GW of demand connection applicationsOfgem consultation · 29 Jul 2026
At least 80 GW
Data-centre applications (at least 64%)
Up to 45 GW
Remaining applications and unassigned share

This is a queue of requests, not electricity currently consumed. The remaining segment must not be treated as a verified non-data-centre total. Figures are national, not Teesworks-specific.

Calculated minimum share: 80 ÷ 125 = 64%. Underlying Ofgem figures are rounded; the plotted 64% is an illustrative lower bound, not a forecast of built capacity.

National Grid’s broader work to connect large users is part of the backdrop, but this land agreement is its own project. A planned substation can enable future investment without ensuring that every proposed data hall will be financed or occupied.

Documented milestones

What has actually happened, and what is pending?

The two council records offer a firmer chronology than headlines about Europe’s possible largest data-centre campus. The substation application remains live even though a different data-centre planning stage has already been approved.

1 Aug 2025Planning approval
Data-centre campus reserved matters approved

Redcar and Cleveland granted approval to Teesworks Ltd for the separate campus application R/2025/0382/ESM.

24 Sep 2026Application received
400kV substation application submitted

National Grid Electricity Transmission filed outline application R/2026/0711/OOM for land west of Tees Dock Road.

1 Oct 2026Consultation opens
Council consultation starts

The public consultation for the substation is listed as running until 11 November 2026.

Late Oct 2026Exact day undisclosed
Land deal agreed

Sky News said the agreement was signed in the preceding week; it did not supply an exact signing date.

1 Nov 2026Public reporting
National Grid and Teesworks statements reported

The report connects the substation to potential large-scale AI development. No completed power facility or named campus operator was announced.

11 Nov 2026Upcoming as at publication
Listed consultation deadline

The council record gives this date for comments, not for approval or completion.

The phrase “Europe’s largest data centre” is a reported ambition, not a certified ranking of an operating facility. Without a final announced customer, electricity allocation and operational capacity, it would be premature to compare the finished campus with live data-centre sites.

Four gates still separate the deal from a running campus
01Planning decision

Determine the substation application and any remaining consents.

02Site preparation

Complete land remediation, handover and enabling works.

03Commercial decisions

Confirm the campus developer, tenant, investment and connection terms.

04Build and energise

Commission electrical infrastructure and data-centre phases.

Sequence is an explanatory overview, not an announced construction schedule. Some commercial and construction steps may overlap.
Regional and digital impact

What could the project mean for Teesside and UK broadband?

A large data-centre campus would need both power and substantial external network connections. That can create opportunities for new fibre routes, transport capacity and skilled infrastructure jobs. It does not automatically mean faster home broadband or lower bills for nearby residents.

Investment and employment

Construction and specialist engineering work could grow if the scheme proceeds. Job totals and the eventual operator have not been confirmed in a final project announcement.

Electricity and bill protections

The crucial issue is how grid-upgrade costs are allocated. The Government’s October Data Centre Covenant calls for strategic projects to protect consumers and contribute to energy-system costs.

Environmental conditions

Remediation of former industrial land, water demand, cooling and energy efficiency require scrutiny as designs become more detailed. Planning approval is not the same as an environmental blank cheque.

Fibre and data movement

Modern AI systems need high-volume AI traffic links and resilient national and international paths, including the subsea fibre routes that support the UK internet.

A useful test for future updates is to look for a named data-centre customer, an approved substation scheme, a published construction timetable and confirmed power connection milestones. Each would add evidence of progress. None can be inferred from a land purchase alone.

Ties the meerkat
Ties’ verdict

The land agreement moves a potentially important Teesside grid project forward. It does not yet turn the proposed AI campus into a completed, powered facility. Watch the planning record and the first confirmed tenant rather than the superlatives.

Explore the infrastructure
Clear answers

Frequently asked questions

Has National Grid bought the Teesside data centre?

No. The reported agreement concerns more than 70 acres of Teesworks land intended for a proposed electricity substation. National Grid has not announced that it is buying or operating a data centre.

Where is the new National Grid substation planned?

At Dorman Point in the Teesworks industrial regeneration area on Teesside, east of Middlesbrough. National Grid calls it the proposed Tees Dock substation.

Has the Teesside data-centre project received planning permission?

A Teesworks data-centre campus received reserved-matters approval on 1 August 2025. National Grid’s separate 400kV substation outline application had no recorded decision as of 1 November 2026.

Will the site definitely use 3.2GW of electricity?

No. The Tees Valley mayor referred to potential capacity of up to 3.2GW. That is not an independently verified operational load, guaranteed power supply or announced data-centre consumption figure.

Hasnaat Mahmood
Hasnaat MahmoodBroadband and technology writer

Hasnaat Mahmood writes about broadband, telecommunications and consumer technology for Find Cheap Broadband. His articles help readers understand internet services, compare their options and make more informed choices.

Key sources
  1. Sky News, 1 November 2026: National Grid Teesside land dealOriginal report on the 70-plus-acre agreement, company statements, reported 3.2GW potential and unconfirmed data-centre partner.
  2. National Grid: Tees Dock substation proposalNational Grid’s official project listing identifies the planned substation at Dorman Point.
  3. Redcar and Cleveland Council: substation application R/2026/0711/OOM24 September submission, 400kV outline proposal, consultation deadline and lack of a decision at publication.
  4. Redcar and Cleveland Council: data-centre campus R/2025/0382/ESMSeparate 1 August 2025 reserved-matters approval for the data-centre campus.
  5. Ofgem, 29 July 2026: grid connection queue reformSource for 125GW demand connection applications, of which at least 80GW are data-centre projects.
  6. HM Treasury, 28 October 2026: Data Centre CovenantGovernment expectations on power system costs, community benefits, jobs and environmental standards.